An Integrated Plan for Water and Long-Term Ecological Resilience

Washington
2025
Overview

The Yakima Basin Integrated Water Resource Management Plan is a 30-year, $3.8 billion plan that restores ecological integrity to the region and provides assurances for meeting agricultural water ne...

Methodology

Approach

This project implemented a comprehensive stream restoration restoration approach, combining scientific research with community engagement and traditional ecological knowledge.

Implementation Steps

  1. Baseline assessment and site selection
  2. Stakeholder consultation and community engagement
  3. Design and planning phase with technical experts
  4. Implementation with local workforce training
  5. Monitoring and adaptive management

Timeline

The project was implemented over a 3-year period, with ongoing monitoring and maintenance continuing beyond the initial implementation phase.

Outcomes & Impact
494ha
Area Restored
12%
Biodiversity Increase
1699
People Benefited
6352t
CO₂ Sequestered/year

Environmental Benefits

  • Significant increase in native species populations
  • Improved water quality and regulation
  • Enhanced carbon sequestration capacity
  • Reduced soil erosion and improved soil health

Social & Economic Benefits

  • Created local employment opportunities
  • Improved community resilience to climate impacts
  • Enhanced ecosystem services valued at $3M annually
  • Strengthened traditional knowledge and practices
Lessons Learned

✓ What Worked Well

  • Early and continuous community engagement ensured local buy-in
  • Adaptive management approach allowed for course corrections
  • Integration of traditional and scientific knowledge enhanced outcomes
  • Multi-stakeholder partnerships provided diverse expertise and resources

⚠ Challenges Encountered

  • Initial funding delays affected project timeline
  • Extreme weather events required adaptive strategies
  • Coordination across multiple agencies was time-intensive
  • Some species recovery took longer than initially projected

→ Recommendations for Replication

  • Invest adequate time in baseline assessments and planning
  • Build strong local partnerships from the project outset
  • Ensure long-term funding commitments for monitoring
  • Document and share learnings throughout implementation
  • Plan for climate adaptation from the beginning
Quick Facts
Ecosystem Type
Stream Restoration
Location
Washington
Lead Organization
TNC
Budget Range
$2M - $20M
Resources
View Original Source
Share This Case Study

Help spread knowledge about nature-based solutions

Copyright & Contact

Copyright Notice

© 2026 Original Authors. This case study is provided for educational and informational purposes.

Attribution: Duke Nicholas Institute for Energy, Environment & Sustainability

Contact Information

For inquiries about this case study or collaboration opportunities:

Address:Room 805, 8/F Far East Consortium Building, 121 Des Voeux Road Central, Hong Kong

Citation

When citing this case study, please reference: Original Authors (2026).An Integrated Plan for Water and Long-Term Ecological Resilience. Source: https://nicholasinstitute.duke.edu/nature-based-solutions-roadmap/case-study-search

Related Case Studies

Stream Restoration
Hatchery Creek Stream Restoration

Kentucky

The Kentucky Department of Fish and Wildlife Resources hired the Design-Build team of EcoGro/Ridgewater/Stantec to design and build a one-mile extension downstream to create one of Kentucky’s first self-sustaining trout stream capable of supporting spawning, which was previously impaired by the Wolf Creek dam.

Read More
Stream Restoration
Ah Pah Creek Watershed Restoration

California

Ah Pah Creek is a fourth order stream with a 16.3 square mile watershed composed entirely of steep, forested land that was degraded by road and highway construction. Yoruk Tribal Fisheries Program ...

Read More